APPENDIX - XXVI

(Referred to in paragraph 12.10.3.2 at page 68)

Levy of penalty on delayed works

Sl.
No.

Name of work

Tendered Cost (Rs in lakh)

Scheduled Date of Completion

Actual Date of Completion

Delay in Months

Compensation levied (Rs)

Percentage

Gujarat

1

C/o Additional 6TY IV SQ at Bharuch

25.62

02.07.1998

27.2.1999

08

10033

0.33

2

C/o Additional 6TY IV SQ at Akota, Baroda

23.21

04.05.1998

30.10.1999

18

13050

0.56

3

V/E to Addl 4 TY V SQ at Akota

29.38

20.11.1998

30.10.1999

11

15000

0.51

4

V/E at TE building at Makarpura

35.21

08.10.1997

11.05.1998

08

7895

0.22

5

6 TY III SQ at Pandesara, Surat

16.07

02.10.1997

30.10.1999

24

13726

0.88

Orissa

1

C/o VE to TE Building at Khurda

12.99

8.02.2000

29.70.2000

18

7500

0.57

2

C/o 6 Nos. TY I, 12 No. TY II and 6 No. TY III SQ at Koraput

30.46

16.08.1997

30.05.1998

10

10000

0.32

3

C/o One No. Type IV 2 Nos. Ty II and 2 Nos. Type II SQ at Paralakhemundi

22.79

04.11.1998

29.01.2000

14

10000

0.21

West Bengal

1

C/o 8 No. Type-II, 8 Nos. Type III and 2 No. Type-IV SQ at Koneradilu, Bankara

50.53

19.08. 1996

31.08. 1998

24

8925

0.17

2

C/o 3 Nos. Type-II and 3 No. Type-III SQ at Memasi

17.17

08.03. 1997

28.02. 1998

12

2610

0.15

3

C/o 1 No. Type-II and 2 No. Type-III SQ at Pumlia

7.68

10.01. 1996

30.09. 1996

08

219

0.02

4

Misc work for shifting C/M rest room and store room at Jalpaiguri TE Building

0.38

23.02. 1999

07.06. 1999

3.5

100

0.02

Tamil Nadu

1

C/o Sqrs at Usilampatti

22.46

12.12. 1997

26.11. 1998

12

31806

0.01

2

C/o Sqrs at KK Nagar, Madurai

15.69

02.02. 1998

15.01. 1999

12

21005

0.01

3

C/o CDOT Building at Karaikudi

95.52

04.12. 1998

24.09. 1999

09

31000

0.32

4

C/o TE Building at Aruppukottai

98.07

14.08. 1998

15.06. 1999

09

88077

0.89

5

C/o Sqrs at Palani

19.35

07.01. 1999

28.12. 1999

11

9700

0.50

6

C/o Sqrs at Mannargudi

16.85

10.06. 1996

05.09. 1997

15

1290

0.07

7

C/o Sqrs at Gudalur

65.46

30.03. 1996

27.10. 1997

19

300

0.0040

8

C/o Sqrs at Thondamothur

9.70

26.01. 1998

29.05. 1998

04

530

0.0050

9

C/o Community Centre at Thayagam Road, Coimbatore

25.06

08.03. 1999

11.08. 1999

5

3780

0.001

10

C/o TE Building at Achinnatharapuram

25.06

08.03.1999

11.08. 1999

5

38555

0.01

11

C/o SQ at Dalmiapuram

16.67

27.06.1999

29.02.2000

8

11606

0.007

12

C/o SQ at Poompuhar

25.51

11.12.1998

31.08.2000

20

16240

0.006