Delay in handing over of telephone exchange building

Sl
No.

Name of the circle

No. of
cases

Delay in
months

Reason

Financial Implications
(Rs in crore)

1.

Ahmedabad

20

4-21

Delay on the part of agency and slow progress of works

102.44

2.

Calcutta

1

39-56

Telecom. authorities not taken over and administrative reasons

0.45

 

Total

21

   

102.89
Say 103 crore