APPENDIX - XXII

(Referred to in paragraph 12.10.2.1 at page 66)

Delay in completion of works due to departmental reasons

Sl.
No.

Name of the Circle

No. of
cases

Delay
(in days)

Reasons for department delay

Extra amount if any paid underclause Sec. 10CC
(Rs in lakh)

1

Andhra Pradesh

39

25-230

NA

21.63

2

Bihar

37

30-1106

NA

71.21

3

Chennai Telephones

5

79-651

-do-

53.55

4

Gujarat

12

30-404

Non completion of electrical work, non-receipt of floor plan, delay in supply of drawings, non-availability of cement and water logging

28.39

5

Karnataka

17

62-300

Delay in structural drawings electrical work labour problem clear site, heavy rain

7.65

6

Kerala

43

12-594

Change of foundation laying of electrical conduits

28.39

7

Maharashtra

2

505-516

Non-approval of building plan/non receipt of drawings acute shortage of water and labour

11.68

8

Punjab

14

194-299

Non-clearance of site/non completion of work by Electrical Wing, non availability of drawings

2.49

9

Rajasthan

9

100-316

Layout not given in time

35.74

10

Tamil Nadu

16

87-306

Non-availability of clear site and non laying of elec. Conducts

18.91

11

Uttar Pradesh (East)

26

 

NA

41.39

12

Uttar Pradesh (West)

48

 

NA

34.66

13

West Bengal

17

69-742 days

Non-coordination between Civil & Electrical, delay in issue of structural drawings, technical problem

22.50

 

Total

285

   

378.19